Financials
As the project progresses, I will update this page with any associated costs. I will be as transparent and specific as possible, as I hope this will be a useful resource for anyone that may be contemplating a similar project. Some services are priced as a package, making itemized details impossible.
| Primary Lots | Lot A | 6767.08 m² | ||
| Lot B | 2257.77 m² | |||
| Total | 9024.85 m² | @$2.55 per m² | $23,000.00 | |
| Notary – Sworn Declaration | 98.20 | |||
| Notary – Deed Transfer | 163.75 | |||
| Secondary Lots | Lot C | 2458.45 m² | ||
| Lot D | 402.88 m² | |||
| Total | 2861.33 m² | @$1.75 per m² | $5,000.00 | |
| Lawyer – Buy/Sell Contract | 30.00 | |||
| Total | $28,291.95 |
| Water | ||||
| Water Rights | $900.00 | |||
| Electricity | ||||
| Total | $900.00 |
| Land Survey | $50.00 | |||
| Turnkey Construction | *Cost Details | 130,000.00 | ||
| Total | $130,050.00 |
| Material Changes | ||||
| Stairs | Cement/Ceramic to Wood | $800.00 | ||
| Total | $800.00 |