Financials

As the project progresses, I will update this page with any associated costs. I will be as transparent and specific as possible, as I hope this will be a useful resource for anyone that may be contemplating a similar project. Some services are priced as a package, making itemized details impossible.

Expense Totals

Category Spending Status Totals
 Land Aquisition CLOSED $28,364.13
Utilities OPEN 956.54
 Architect OPEN 130,050.00
 Home Upgrades OPEN 1,880.00
Equipment OPEN 2,458.00
Total $163,708.67

 

 

Itemized Expenses

Primary Lots Lot A 6767.08 m²
Lot B 2257.77 m²
Total 9024.85 m² @$2.55 per m² $23,000.00
Notary Work 261.95
Deed Submission 37.59
Secondary Lots Lot C 2458.45 m²
Lot D 402.88 m²
Total 2861.33 m² @$1.75 per m² $5,000.00
Lawyer – Buy/Sell Contract 30.00
Deed Submission 34.59
Total $28,364.13

Water
  Water Rights $900.00
Electricity
  Site Inspection 14.42
  Property Certificate 25.00
  Meter 17.12
  Total $956.54

Land Survey $50.00
Turnkey Construction ≈ $42 / sq. ft *Cost Details 130,000.00
Total $130,050.00

Material Changes
  Stairs From Ceramic to Wood $800.00
Additions
  Balcony 600.00
  Extra Outlets 480.00
Total $1,880.00

Appliances
Wood Stove $2,458.00
Networking
 
Security
 
Total $2,458.00

Contact

Email  –  [email protected]

Whatsapp  –  +593 99 367 6787

Text  –  +1 828 545 1610

Subscribe

Be notified when future posts go live.

Loading